Client Aggregate Industries UK- Uttoxeter Quarry
Contractor RFS Works Limited
Date 2019
Volume Circa 260k m3
Stripping top soils and OB (clay) with excavators loading to ADT`s, hauling and placing within the quarry lakes restoration works.

Utilising 2 x CAT 352LME excavators with 3.5m3 mass ex buckets for the stripping & loading of clay materials to 4 x 45t ADT`s and 4 x 30t ADT`s, operations in a fully operational quarry environment where dredging is used to win the minerals, all OB materials are placed into lakes to restore the quarry workings with full GPS Lgp dozers. All surveying and management of a full inclusive on site earthworks package and restoration scheme with material deposition areas in water for the quarry restoration